Permits for public sewer systems must be approved or denied within how many working days?

Study for the West Virginia Septic Installer Test. Prep with flashcards and multiple-choice questions, each accompanied by hints and explanations. Ace your exam with comprehensive resources!

Permits for public sewer systems must be approved or denied within 45 working days to ensure a timely and efficient process for developers and municipalities. This timeframe is established to facilitate quick responses, enable effective planning, and maintain the progress of construction projects. By limiting the decision-making period to 45 days, it strikes a balance between allowing sufficient time for review and analysis while preventing unnecessary delays in the provision of essential sewer services. Understanding this time frame is crucial for those involved in the permitting process, as it impacts project timelines and fulfills regulatory requirements for public health and safety.